Who says you can't pour concrete in the snow.
8 days until the timber frame arrives! Honest.
Saturday, 27 November 2010
Friday, 26 November 2010
Concrete is coming
we're getting closer. The formwork is coming on and lounge slab is now ready, although you wouldn't guess from this photo, for concrete tomorrow.
Thursday, 25 November 2010
It's taking shape
The lounge slab is excavated and weather permitting will be cast on Saturday
Formworks going in ready for the basaement lid to be cast early next weekAll of this has been good news and great progress, but todays other activity has been unblocking next doors drains.
That's right, next doors foul drain was weeping into our site, that puddle is not rainwater, I know because I've smelt it and then lifted 4 of nextdoors manhole covers to find the blockage.
It wasn't the best morning I've had.
Wednesday, 24 November 2010
Filled to the top
Tuesday, 23 November 2010
Friday, 19 November 2010
Concrete (Take 2)
Here we go again, more concrete being pumped into the basement walls
That's it, the walls are full . . . . . . and standing.
Thursday, 18 November 2010
Tuesday, 16 November 2010
Tank 'eavans
At last the basement is taking shape with the Tanking primer in place. Another day or so and we can start to back fill this ever increasing hole in the ground.
Wednesday, 10 November 2010
Friday, 5 November 2010
More Blocks
Look very carefully and you can now see it from the road. Just under that lovely red sign.
By next Wednesday it'll be concreted and thne it's only 2 and half weeks until all groundworks are complete.
Thursday, 4 November 2010
Subscribe to: