Monday, 13 June 2011

Scaffolds down!

Well, half of it is. And the first section of timber cladding is on.



Saturday, 4 June 2011

Forget the basement and carry on

With water coming into the basement there was nothing we could do but carry on with works above ground.


So it was on with installing the membrane and room edges, ready to take the


underfloor heating pipes



and then the screed. We now finally have the floor up to the correct level


after months of struggling with large first steps and impossible thresholds.


Here's manifold 1 for those of you who like this sort of thing. and if you do you'll love next week as 2 more will be installed.


We've also had our first intruder on site. The evidence is there for all to see.